Liquidated Damages are the financial mirror of an Extension of Time - if a delay is the contractor's fault, damages start accruing; if a valid EOT is granted instead, the completion date itself moves and damages don't apply, which is exactly why the underlying schedule and change documentation matters so much to both sides.