LOD defines how detailed and reliable an element in the BIM model is at a given stage. It answers the question: "How much can I trust this model element, and what information does it contain?"
The standard LOD scale runs from 100 to 500:
| LOD | Stage | What it means |
|---|---|---|
| 100 | Concept | Element exists as a symbol or mass. Size and location are approximate. |
| 200 | Schematic Design | Generic element with approximate geometry and size. |
| 300 | Design Development | Specific geometry, exact dimensions, location, and orientation. |
| 350 | Construction Documents | Includes connections to adjacent elements. Ready for coordination. |
| 400 | Fabrication | Detailed enough for manufacturing and assembly. |
| 500 | As-Built | Verified in the field. Represents the building as actually constructed. |
LOD is used in the BEP to specify what level each model element must reach at each project milestone.